Central Chilterns Community Forum Area - Public Rights of Way |
|
All
details on this document are assumptions based on current design work and are
subject to change as design develops. |
|
|
|
|
|
PRoW/Ref |
Structure/HS2
Chainage |
Impacts During
Construction |
Impact After
Construction |
Duration of
Works |
LMI/17/2 (Public footpath) |
044+700 |
Footpath
diverted through Mantle's Farm onto Public Footpath (TBC) Crossing route of
HS2 over bored tunnel at 044+300. Footpath LMI/17/2 re-instated on existing
alignment following completion of bored tunnel works. |
Approx
additional length of permanent diversion - negligible. |
No
data |
GMI/23/7 (Public footpath) |
045+150 |
Temporary/permanent
diversion dependent on whether Hyde Farm Accommodation bridge goes
ahead. |
Approx
additional length of permanent diversion - 200m. |
No
data |
GMI/27/1 (Public footpath and private access) |
045+500 |
Temporary/permanent
diversion dependent on whether Hyde Farm Accommodation bridge goes
ahead. |
Approx
additional length of permanent diversion - negligible. |
No
data |
GMI/33/3, GMI/33/2 (Public footpath) |
045+900 |
Permanent
diversion along north side of HS2, from Hyde Lane to tie-into existing
footpath at approximate Ch 46+000. |
Approx
additional length of permanent diversion - 100m. |
No
data |
GMI/33/4 (Public footpath) |
046+100 |
Permanent
diversion along south side of HS2, from Hyde Lane to South Heath Green Tunnel
South Portal access track. Possible temporary diversion during construction
of access track. |
Approx
additional length of permanent diversion - 100m. |
No
data |
GMI/80/1, 79/1, 28/2, 79/2, 28/1 (Public footpath) |
046+700 |
Temporary
closure of footpaths between Chesham Road and King's Lane/Sibley's Rise. Footpath users diverted along Chesham Road
and King's Lane. Possible issue with King's Road as no there is no
discernible verge or footway for footpath users. |
Approx
additional length of permanent diversion - 0m. |
No
data |
GMI/13/3 (Public footpath) |
047+450 |
Footpath
remains open during construction of overbridge at Ch 47+800 where it is then
permanently diverted. |
Approx
additional length of permanent diversion - 750m. |
app
6 - 9 months |
GMI/12/1 (Public footpath and private access) |
047+800 |
Footpath
and private access remain open during construction of the overbridge
structure, with slight temporary diversion along the boundary of construction
works. |
Approx
additional length of permanent diversion - 0m. |
app
4 - 6 months |
GMI/2/1 (Public footpath) |
048+150 |
Footpath
remains open during construction of accommodation overbridge at Ch 48+400
where it is then permanently diverted. |
Approx
additional length of permanent diversion - 550m. |
No
data |
Accommodation Bridge 1 Ch.48400 |
048+400 |
Private
access remains open during construction of the overbridge structure, with
slight temporary diversion along the boundary of construction works. |
Approx
additional length of permanent diversion - negligible. |
app
9 - 12 months |
|
HS2 Ltd
November '12 |
|
|
|
|
|
|