| Central Chilterns Community Forum Area - Public Rights of Way | ||||
| All details on this document are assumptions based on current design work and are subject to change as design develops. | ||||
| PRoW/Ref | Structure/HS2 Chainage | Impacts During Construction | Impact After Construction | Duration of Works |
| LMI/17/2 (Public footpath) | 044+700 | Footpath diverted through Mantle's Farm onto Public Footpath (TBC) Crossing route of HS2 over bored tunnel at 044+300. Footpath LMI/17/2 re-instated on existing alignment following completion of bored tunnel works. | Approx additional length of permanent diversion - negligible. | No data |
| GMI/23/7 (Public footpath) | 045+150 | Temporary/permanent diversion dependent on whether Hyde Farm Accommodation bridge goes ahead. | Approx additional length of permanent diversion - 200m. | No data |
| GMI/27/1 (Public footpath and private access) | 045+500 | Temporary/permanent diversion dependent on whether Hyde Farm Accommodation bridge goes ahead. | Approx additional length of permanent diversion - negligible. | No data |
| GMI/33/3, GMI/33/2 (Public footpath) | 045+900 | Permanent diversion along north side of HS2, from Hyde Lane to tie-into existing footpath at approximate Ch 46+000. | Approx additional length of permanent diversion - 100m. | No data |
| GMI/33/4 (Public footpath) | 046+100 | Permanent diversion along south side of HS2, from Hyde Lane to South Heath Green Tunnel South Portal access track. Possible temporary diversion during construction of access track. | Approx additional length of permanent diversion - 100m. | No data |
| GMI/80/1, 79/1, 28/2, 79/2, 28/1 (Public footpath) | 046+700 | Temporary closure of footpaths between Chesham Road and King's Lane/Sibley's Rise. Footpath users diverted along Chesham Road and King's Lane. Possible issue with King's Road as no there is no discernible verge or footway for footpath users. | Approx additional length of permanent diversion - 0m. | No data |
| GMI/13/3 (Public footpath) | 047+450 | Footpath remains open during construction of overbridge at Ch 47+800 where it is then permanently diverted. | Approx additional length of permanent diversion - 750m. | app 6 - 9 months |
| GMI/12/1 (Public footpath and private access) | 047+800 | Footpath and private access remain open during construction of the overbridge structure, with slight temporary diversion along the boundary of construction works. | Approx additional length of permanent diversion - 0m. | app 4 - 6 months |
| GMI/2/1 (Public footpath) | 048+150 | Footpath remains open during construction of accommodation overbridge at Ch 48+400 where it is then permanently diverted. | Approx additional length of permanent diversion - 550m. | No data |
| Accommodation Bridge 1 Ch.48400 | 048+400 | Private access remains open during construction of the overbridge structure, with slight temporary diversion along the boundary of construction works. | Approx additional length of permanent diversion - negligible. | app 9 - 12 months |
| HS2 Ltd November '12 | ||||