Central Chilterns Community Forum Area - Public Rights of Way
All details on this document are assumptions based on current design work and are subject to change as design develops.
PRoW/Ref Structure/HS2 Chainage Impacts During Construction Impact After Construction Duration of Works
LMI/17/2 (Public footpath) 044+700 Footpath diverted through Mantle's Farm onto Public Footpath (TBC) Crossing route of HS2 over bored tunnel at 044+300. Footpath LMI/17/2 re-instated on existing alignment following completion of bored tunnel works.  Approx additional length of permanent diversion - negligible. No data
GMI/23/7 (Public footpath) 045+150 Temporary/permanent diversion dependent on whether Hyde Farm Accommodation bridge goes ahead.  Approx additional length of permanent diversion - 200m. No data
GMI/27/1 (Public footpath and private access) 045+500 Temporary/permanent diversion dependent on whether Hyde Farm Accommodation bridge goes ahead.  Approx additional length of permanent diversion - negligible. No data
GMI/33/3, GMI/33/2 (Public footpath) 045+900 Permanent diversion along north side of HS2, from Hyde Lane to tie-into existing footpath at approximate Ch 46+000.   Approx additional length of permanent diversion - 100m. No data
GMI/33/4 (Public footpath) 046+100 Permanent diversion along south side of HS2, from Hyde Lane to South Heath Green Tunnel South Portal access track. Possible temporary diversion during construction of access track.  Approx additional length of permanent diversion - 100m. No data
GMI/80/1, 79/1, 28/2, 79/2, 28/1 (Public footpath) 046+700 Temporary closure of footpaths between Chesham Road and King's Lane/Sibley's Rise.  Footpath users diverted along Chesham Road and King's Lane. Possible issue with King's Road as no there is no discernible verge or footway for footpath users.  Approx additional length of permanent diversion - 0m. No data
GMI/13/3 (Public footpath) 047+450 Footpath remains open during construction of overbridge at Ch 47+800 where it is then permanently diverted. Approx additional length of permanent diversion - 750m. app 6 - 9 months
GMI/12/1 (Public footpath and private access) 047+800 Footpath and private access remain open during construction of the overbridge structure, with slight temporary diversion along the boundary of construction works.  Approx additional length of permanent diversion - 0m. app 4 - 6 months
GMI/2/1 (Public footpath) 048+150 Footpath remains open during construction of accommodation overbridge at Ch 48+400 where it is then permanently diverted. Approx additional length of permanent diversion - 550m. No data
Accommodation Bridge 1 Ch.48400 048+400 Private access remains open during construction of the overbridge structure, with slight temporary diversion along the boundary of construction works.  Approx additional length of permanent diversion - negligible. app 9 - 12 months
HS2 Ltd November '12