Central Chilterns Community Forum Area - Road Crossings / Realignments
All details on this document are assumptions based on current design work and are subject to change as design develops.
Road Reference Structure/HS2 Chainage Impact During Construction Indicative Construction Period Impact After Construction
Hyde Lane Overbridge 045+780 No diversion route required as offline crossing proposed. Traffic management required during construction of tie-in. app 1 - 1.5 years Minimal as traffic uses new road.  Existing road will be removed.  
B485 Chesham Road 046+300 No diversion route required as offline crossing proposed. Traffic management required during construction of tie-in. No data Minimal as traffic uses new road.  Existing road will be retained in part to maintain access to existing properties. 
Kings Lane 046+400 Temporary road closure. Diversion via B485 Chesham Road and Frith Hill.  No data Minimal as traffic uses new road.  Existing road will be removed.  
Frith Hill 047+100 Temporary road closure. Diversion via B485 Chesham Road and King's Road.  No data Minimal as traffic uses new road. 
Leather Lane Overbridge 048+800 No diversion route required as offline crossing proposed. Traffic management required during construction of tie-in. app 9 - 12 months Minimal as traffic uses new road.  Existing road will be removed.  
HS2 Ltd - November 2012