Central Chilterns Community Forum Area - Current estimates on construction compound details
All details on this document are assumptions based on current design work and are subject to change as design develops.
Worksite Location Structure/HS2 Chainage Servicing Operation Period of Operation Staff numbers Construction access route to worksite
A413 Vent Shaft
43+000
Little Missenden Vent Shaft Secondary app 6 - 9 months Circa 50 A413
Chiltern Tunnel North Portal Tunnel Portal
44+700
Chiltern Tunnel,  Secondary app 6 - 9 months Circa 100 Upgraded access (via Hyde Heath Rd)
South Heath Green Tunnel Green Tunnel
46+400
Hyde Lane, Chesham Lane ATS
South Heath Green Tunnel, Chesham Road, Kings Lane, Frith Hill
Secondary app 5 - 5.5  years (single face working), 2.5 - 2.75 years (double face working) Circa 50 B485 Chesham Road 
South Heath Green Tunnel Green Tunnel
47+400
South Heath Green Tunnel Secondary app 5 - 5.5  years (single face working), 2.5 - 2.75 years (double face working) Circa 50 Frith Hill
Leather Lane Overbridge
48+700
Leather Lane Overbridge Secondary app 1.5 - 2 years Circa 50 Leather Lane (Kings Lane)
HS2 Ltd - November '12