Dunsmore Wendover & Halton Community Forum Area - Public Rights of Way
PRoW/Ref Structure/HS2 Chainage Impacts During Construction Impact After Construction Duration of Works
Accommodation Bridge 2 Ch.49300 049+300 Private access remains open during construction of the overbridge structure, with slight temporary diversion along the boundary of construction works.  Approx additional length of permanent diversion - negligible 6-9months
TLE/2/2 - public footpath  049+800 Private access remains open during construction of the overbridge structure, with slight temporary diversion along the boundary of construction works.  Approx additional length of permanent diversion - 0m 6-9months
TLE/3/1 (public footpath) 050+125 Footpath remains open during construction of TLE/2/2 Footbridge at Ch 49+800, then is temporarily diverted onto this footbridge until completion of Bowood Lane Overbridge.   Approx additional length of permanent diversion - 0m 9-12months
WEN/36/1 (Public footpath and private access) 050+700 Footpath and private access temporarily diverted. Footpath re-instated on permanent diversion route following completion of viaduct works.  Approx additional length of permanent diversion - negligible No data
WEN/39/2 (Public footpath and private access) 051+025 Footpath and private access temporarily diverted. Footpath re-instated on permanent diversion route following completion of viaduct works.  Approx additional length of permanent diversion - 0m 6-9months
Grove Farm  53+200 Private access remains open during construction of underpass at Ch 53+300 where it is then permanently diverted. Approx additional length of permanent diversion - negligible 6-9months
WEN/14/4 (Public bridleway) 053+900 Local diversion of bridleway to suit construction of green tunnel as required. Bridleway remains open during construction of Green Tunnel section at Ch 54+000 where it is then permanently diverted. Approx additional length of permanent diversion - 200m 6-9months
WEN/13A/A(Public footpath) 054+000 Local diversion of footpath to suit construction of green tunnel as required.  Approx additional length of permanent diversion - 0m No data
WEN/11/1, 11/2
(Two public footpaths)
054+300 Local diversion of footpath to suit construction of green tunnel as required. Permanent diversion to suit green tunnel bund.  Approx additional length of permanent diversion - 0m No data
WEN/55/1
(Public footpath)
054+875 Local diversion of footpath to suit construction of green tunnel as required. Permanent diversion to suit green tunnel bund.  Approx additional length of permanent diversion - 0m No data
ELL/25/1 (Public footpath and Private Access) 056+000 Footpath remains open during construction of Nash Lee Road Overbridge and permanent footpath diversion route.  Approx additional length of permanent diversion - negligible No data
All details on this document are assumptions based on current design work and are subject to change as design develops.
HS2 Ltd - Nov '12