Dunsmore, Wendover & Halton Community Forum Area - Road Crossings / Realignments
Road Reference Structure/HS2 Chainage Impact During Construction Indicative Construction Period Impact After Construction
Bowood Lane Overbridge 050+100 Temporary road closure. Diversion via A413 London Road, Rocky Lane/Chesham Lane and King's Lane.  9-12 months Minimal as traffic uses new road.
Small Dean Lane 053+000 Temporary road closure. Diversion via A413 London Road and Dunsmore Lane.   No data Minimal as traffic uses upgraded existing road. 
(Access track) 053+450 None, permanent diversion to be constructed prior to closure.  6-9 months Minimal as traffic uses new road.
Bacombe Lane Link 053+950 None No data Traffic uses new link road. Approximate additional length of pemanent diversion 600m. Green tunnel will cover route of existing Bacombe Lane. 
Ellesborough Road 054+200 Temporary road closure. Diversion via temporary link to east of Ellesborough Road.  No data Minimal as traffic uses new road. 
B4009 Nash Lee Road Overbridge 056+000 No diversion route required as offline crossing proposed. Traffic management required during construction of tie-in. 12-18 months Minimal as traffic uses new road. 
Nash Lee Lane 056+125 None, permanent diversion to be constructed prior to closure.  6-9 months Minimal as traffic uses new road. 
(Private access) 056+500 None, permanent diversion to be constructed prior to closure.  6-9 months  Approximate addtional length of permanent diversion via Nash Lee Road and Nash Lee Lane 1000m. 
All details on this document are assumptions based on current design work and are subject to change as design develops.
HS2 Ltd - Nov '12