Dunsmore Wendover & Halton Community Forum Area - Current estimates on construction compound details | ||||||
Worksite Location | Structure/HS2 Chainage | Servicing | Operation | Period of Operation | Staff numbers | Construction access route to worksite |
Bowood Lane | 50+100 | Bowood Lane Overbridge, Wendover Dean Viaduct, | Secondary | app 1.5 - 2 years | Circa 50 | Bowood Lane |
Wendover Dean Viaduct Launch | Viaduct 51+000 |
Wendover Dean Viaduct | Secondary | app 1.5 - 2 years | Circa 100 | Haul
Road (via Rocky Lane) |
Rocky Lane | Underbridge 51+900 |
Rocky Lane Underbridge, Wendover ATS | Secondary | app 0.5 - 1 year | Circa 50 | Rocky Lane |
Small Dean Viaduct Launch | 52+400 | Small Dean Viaduct | Secondary | app 0.5 - 1 year | Circa 50 | Haul
Road (via Rocky Lane) |
Small Dean Viaduct | Viaduct 52+900 |
Small Dean Viaduct | Primary | app 1.5 - 2 years | Circa 150 | Small Dean Lane |
Bacombe Road | Green
Tunnel 53+600 |
Wendover Green Tunnel, Ellesborough Road | Secondary | app 4.5 - 5 years (single face working), 2.25 - 2.5 years (double face working) | Circa 50 | Access
Road (via A413/Small Dean Lane) |
A413 | Green
Tunnel 55+300 |
Wendover Green Tunnel | Secondary | app 4.5 - 5 years (single face working), 2.25 - 2.5 years (double face working) | Circa 50 | A413 Nash Lee Road |
Nash Lee Road | Overbridge
55+900 |
Nash Lee Road, Nash Lee Lane , Stoke Grove ATS | Secondary | app 1 - 1.5 years | Circa 50 | Nash Lee Lane/A413 |
All details on this document are assumptions based on current design work and are subject to change as design develops. | ||||||
HS2 Ltd - Nov '12 |