Dunsmore Wendover & Halton Community Forum Area - Current estimates on construction compound details
Worksite Location Structure/HS2 Chainage Servicing Operation Period of Operation Staff numbers Construction access route to worksite
Bowood Lane 50+100 Bowood Lane Overbridge, Wendover Dean Viaduct,  Secondary  app 1.5 - 2 years Circa 50  Bowood Lane 
Wendover Dean Viaduct Launch
Viaduct
51+000
Wendover Dean Viaduct Secondary  app 1.5 - 2 years Circa 100 Haul Road
(via Rocky Lane)
Rocky Lane  Underbridge
51+900
Rocky Lane Underbridge, Wendover ATS Secondary  app 0.5  - 1 year Circa 50  Rocky Lane 
Small Dean Viaduct Launch 52+400 Small Dean Viaduct Secondary  app 0.5 - 1 year Circa 50  Haul Road
(via Rocky Lane)
Small Dean Viaduct 
Viaduct
52+900
Small Dean Viaduct Primary  app 1.5 - 2 years  Circa 150 Small Dean Lane 
Bacombe Road Green Tunnel
53+600
Wendover Green Tunnel, Ellesborough Road Secondary  app 4.5 - 5 years (single face working), 2.25 - 2.5 years (double face working) Circa 50  Access Road
(via A413/Small Dean Lane)
A413 Green Tunnel
55+300
Wendover Green Tunnel Secondary  app 4.5 - 5 years (single face working), 2.25 - 2.5 years (double face working) Circa 50  A413 Nash Lee Road 
Nash Lee Road Overbridge
55+900
Nash Lee Road, Nash Lee Lane , Stoke Grove ATS Secondary  app 1 - 1.5 years  Circa 50  Nash Lee Lane/A413
All details on this document are assumptions based on current design work and are subject to change as design develops.